Specialty Grouting

  • High-Yield Two-Component Mine Backfill Grout

High-Yield Two-Component Mine Backfill Grout

High-Yield Two-Component Mine Backfill Grout produces a rapid-setting underground fill with approximately 500-600 kg of dry material per cubic metre.


 High Filling Yield

Approximately 500-600 kg of dry material is required to produce one cubic metre of hardened fill at the stated mix ratio.


 Controlled Gel Time

The combined A and B slurries gel within 20 minutes, with adjustment available for approved project conditions.


 Stable Separate Slurries

The individual A and B slurries have a setting time of at least 24 hours before they are combined.


 Early Support Strength

The filling body develops at least 1.0 MPa after 2 hours, 3.0 MPa after 1 day and 4.5 MPa after 7 days.


Share:

Product Introduction

High-Yield Two-Component Mine Backfill Grout is a prepacked inorganic filling system for underground mining applications. It is supplied as separate Component A and Component B mineral powders.


Each component is mixed with water independently and conveyed through a separate line. The two slurries are combined at a 1:1 volume ratio close to the filling point. After mixing, the grout gels within 20 minutes and forms a stable, water-rich filling body.


At the recommended water-to-powder ratio of 1.5:1, approximately 500-600 kg of dry material is required for one cubic metre of hardened fill. The lower dry-material demand reduces the quantity of material that must be transported underground and supports pipeline placement into enclosed or irregular spaces.


The hardened fill develops at least 1.0 MPa after 2 hours, 3.0 MPa after 1 day and 4.5 MPa after 7 days. It is intended for gob-side entry retaining, empty roadway filling, goaf filling and underground void filling where early support capacity is required.


This is a prepacked two-component high-water backfill system. It is not a tailings-based paste-backfill binder or a conventional concrete admixture.

SW Super High Water Filling Grout



Product Parameters

ParameterSpecification
Material typeTwo-component inorganic mine backfill grout
ComponentsComponent A and Component B
Water-to-powder mass ratio1.5:1
A/B slurry mixing ratio1:1 by volume
Gel time after A/B mixing≤20 min, adjustable within the approved range
Individual A or B slurry setting time≥24 h
Compressive strength, 2 h≥1.0 MPa
Compressive strength, 1 day≥3.0 MPa
Compressive strength, 7 days≥4.5 MPa
Compressive strength, 28 days≥4.5 MPa
Approximate dry-material consumption500-600 kg/m³
Reference standardsMT/T 420-1995; GB/T 39336-2020
Packaging25 kg moisture-resistant bag
Shelf life6 months in unopened dry packaging





Product Usage

Typical Applications


• Gob-side entry retaining and roadside filling

• Goaf filling in underground coal and metal mines

• Filling of abandoned or empty mine roadways

• Underground cavity and void filling

• Roof-contact filling behind retaining structures

• Mine subsidence-control filling

• Filling of irregular underground spaces where concrete placement is difficult


Application Procedure


1. Inspect and isolate the filling area. Install formwork, retaining structures or filling bags where required.


2. Prepare Component A and Component B in separate mixers using the specified water-to-powder ratio.


3. Keep the two slurries in separate tanks and pipelines. Do not allow the components to mix before the designated mixing point.


4. Pump the A and B slurries simultaneously at an equal-volume ratio.


5. Combine both slurries in an in-line mixer immediately before placement.


6. Deliver the mixed grout continuously into the filling area while monitoring flow, pipeline pressure and fill level.


7. Stop placement when the designed volume or filling level has been reached.


8. Flush the pumps, pipelines and mixing unit with clean water immediately after use.


A site trial should be completed before full-scale application to confirm gel time, pumping distance, line pressure and actual material consumption.



Product Documentation

High-Yield Two-Component Mine Backfill Grout

High-Water Inorganic Backfill Material for Underground Mines

Lechada de relleno minero de alta relación agua/material

Lechada inorgánica bicomponente para relleno de galerías vacías, relleno de goaf y relleno de prevención de incendios en mina

Related Products

W-6 Polyurethane Injection Grout (Two‑Component, Closed‑Cell)

W-6 Polyurethane Injection Grout (Two‑Component, Closed‑Cell)

Two‑component PU injection grout that reacts to form a closed‑cell structure for reliable water cut‑off, void filling and slab undersealing. Adjustable gel time, high expansion and frost resistance (≥F200) enable rapid reopen on critical assets such as airport runways.

Bridge Bearing Grouting Material

Bridge Bearing Grouting Material

High-strength non-shrink grouting material for bridge bearings with excellent flowability, durability and bonding performance.

Ultra-Low Viscosity Epoxy Injection Grout

Ultra-Low Viscosity Epoxy Injection Grout

This epoxy injection grout lineup handles cracks from 0.05mm to >0.2mm, boasting tensile strengths ≥20 MPa and shear ≥15 MPa. Models like HP-3 deliver ≥70 MPa compression, making them reliable for wet or dry bonds in tough repairs.

Inorganic Ground Consolidation Grout

Inorganic Ground Consolidation Grout

An inorganic injection grout for strengthening loose coal, fractured rock and disturbed ground in mines, tunnels, shafts and underground chambers.

SW Ultra-High-Yield Mine Void Filling Grout

SW Ultra-High-Yield Mine Void Filling Grout

A two-component inorganic filling grout that uses water-to-powder ratios from 3:1 to 11:1 for economical filling of large underground voids.

MT Expanding Borehole Sealing Grout

MT Expanding Borehole Sealing Grout

An expanding, low-permeability inorganic grout for long-term sealing of gas drainage and other underground mine boreholes.

AquaBond 40 NF Non-Foaming Structural PU Injection Resin

AquaBond 40 NF Non-Foaming Structural PU Injection Resin

A dense, non-foaming structural injection resin that combines water sealing with reinforcement of concrete, rock and underground ground.

Start Enhancing Your Business With a Concrete Solution Today

Our products have undergone rigorous testing at our national testing laboratory (CABR testing center co., ltd). Renowned Fortune Global 500 firms such as China Railway Group Limited, China Communications Construction Company Limited, and Sinohydro are among our esteemed clients.


Contact Us

Contact Us

Tel.:

+86 153 7387 2353 Manager Guo

E-mail:

WhatsApp:

Get in Touch

Get in Touch

CAPTCHA
Copyright © Sino-sina Building Materials Co., Ltd. All Rights Reserved | Sitemap | Powered by Reanod

We Value Your Privacy

In order to improve the website and user experience, this website uses cookies.